Head Energy Solve AS have been awarded a contract for UPS upgrade and installation of arch flash detection at the Brage platform for Wintershall Norge.

The contract has been awarded under Head Energy Solve’s frame agreement with Wintershall Norge for modification services. Head Energy Solve has started the work and commissioning is scheduled for the Brage turnaround in May 2018.

-We are very pleased to win new modification projects from Wintershall. A large part of the installation will take place during the turnaround period next spring, and with several long-lead items, planning and first-class project execution is crucial to project success. The engineering phase is already well underway and we are looking forward to delivering second to none services to Wintershall, says Svenn Kjetil Haveland, General Manager of Head Energy Solve AS.